RWE Hydrogen Lingen
Entity
RWE Generation SE
Site in a Project-Phase
49808
/ Lingen
Niedersachsen
Schuettorfer Str.
https://www.rwe.com/en/press/rwe-generation/2023-03-30-pilot-hydrogen-plant-takes-shape/

The facility is expected to go into operation this autumn. Using electricity from renewables, it will be able to generate up to 290 kilograms of green hydrogen every hour. The hydrogen will be fed into a public hydrogen network or be mixed with gas as a climate-neutral fuel for turbines at the power plant. In the future, it could also be used to supply the mobility market and the hydrogen-ready gas turbine being planned for construction in Lingen by RWE and Kawasaki. 

Site Master Settings

Status
A
V
P
System Info

Modified by
UserPic  Braun, Uwe
Modified
4/24/2023 2:32 PM
Added by
UserPic  Braun (Sysadmin), Uwe
Added
4/22/2023 7:27 AM
Solutions
Solutions

Solution-Reference:

#E1040

No Services yet available.
Enquire in Solutions how we can help you.

Construction
Project Stage:
Construction
Completion Date:
12/2023
Indicator Unit Value
Modelling Status True

Please create Assets first to manage the Mass Balance Processes