The ethylene plant employing Huanqiu Engineering technology has a total of 7 cracking furnaces, including two gas furnaces and five liquid furnaces | weixin | 27 Oct 2024


Dushanzi Petrochemical Tarim Phase II Ethylene Project is accelerating

Petrochemical Industry Going Global Alliance | November 9, 2024

At present, Dushanzi Petrochemical is accelerating the construction of the Tarim 1.2 million tons/year Phase II ethylene project, which will quickly release 1.2 million tons of polyethylene, 450,000 tons of polypropylene, and 100,000 tons of rubber production capacity. At the same time, it can provide 400,000 tons of raw materials per year to drive the development of the downstream industrial chain.

The Tarim 1.2 million tons/year Phase II ethylene project adheres to the innovative and green construction concept and has built 11 major production units, 10 of which use domestic technology (9 use China Petroleum’s own technology); it maximizes the use of domestic technology and localized equipment, with a localization rate of 99%.

At the end of October this year, the first domestically produced dual-end functionalized solution-polymerized styrene-butadiene rubber SSBR3540 F was successfully started up at the 240,000 tons/year SSBR/SBS rubber unit of PetroChina Dushanzi Petrochemical, filling the domestic gap. Currently, the production capacity of solution-polymerized styrene-butadiene rubber of Dushanzi Petrochemical has reached 160,000 tons/year.

#cnpc #petrochina #dushanzi #tarim #ethylene #polyethylene #polypropylene #sbs #rubber #ssbr #china








19th Sep 2024

On September 17, the first large tower hoisting ceremony of the Tarim 1.2 million tons/year Phase II Ethylene Project of Dushanzi Petrochemical Company was held at the Shangku Petrochemical Park in Korla, Xinjiang.

As the first large tower, the quench water tower is the equipment with the largest diameter in the ethylene unit. It took only more than 100 days to complete the manufacturing, setting a record for the manufacturing of large oversized equipment. The main line of this hoisting used a 4,000-ton crane, and it took only 9 days to transport and assemble.

This hoisting marked the entry of the ethylene unit into the equipment installation stage, which kicked off the on-site construction.

The installation of the quenching water tower is the first large tower crane installation of the project, which opens the prelude to the installation of 9 large tower cranes in the entire ethylene unit. It is planned to complete the installation of 9 large tower cranes on October 31, marking a new stage in the construction of the ethylene unit project.

The main function of the cracking gas quenching water tower is to reduce the temperature of the cracking gas and recover low-grade heat at the same time. The cracking gas quenching water tower achieves cooling and partial condensation of the cracking gas through direct countercurrent contact with the quenching water. This process not only helps to reduce the temperature of the cracking gas and separate part of the gasoline in the cracking gas, but also recovers part of the low-grade heat through the quenching water cycle, further improving energy utilization efficiency. This series of operations effectively reduces the temperature of the cracking gas, ensures the normal operation of the cracking gas compressor, greatly reduces the amount of sewage discharged, and improves the energy utilization efficiency of the ethylene unit and reduces energy consumption by recovering low-grade heat.

At present, the overall progress of the project has been completed by 13.6%. It is planned to complete the construction of the underground pipeline network of the entire site on September 20 and the construction of the entire road on October 30. This year's interim goal is to complete 70% of the soil-less construction before the arrival of winter, creating good conditions for installation next year.

The total investment of the Dushanzi Petrochemical Tarim 1.2 million tons/year Phase II ethylene project is 21.88 billion yuan. After completion, it can produce more than 2 million tons of high-end polyolefins and high-performance rubber materials annually, further improving the localization rate of the domestic high-end petrochemical product industry chain supply chain. The basic machinery of the project is scheduled to be completed by the end of 2025, and fully completed and put into production in 2026.