19 Sep 2024, Heavy Lifting News
deugro Delivers with Arrival of Second Shipment for INEOS Project One.
The second shipment with the last 5 massive storage bullets for the INEOS Project One has just arrived on board the MV Fairmaster for discharging in Antwerp.
Both the first shipment with the MV Fairplayer and this voyage from Zhangjiagang, China, were organized by deugro within a tight schedule from order to loading!
The details of the shipment are:
50,572.4m³ Total Volume
6,547.8 metric tons Total weight
24 Sept 2024, INEOS + AG&P INDUSTRIAL
AG&P Industrial (Atlantic, Gulf, & Pacific Company of Manila, Inc.) has completed the fabrication and shipment of the first batch of Outside Battery Limit (OSBL) modules with a total weight of 1,432.47MT for its first-ever European contract with London-based INEOS, the fourth largest chemical company in the world. Fabricated in AG&P Industrial’s state-of-the art fabrication yard in Batangas, Philippines, the modules were shipped to Port of Antwerp, Belgium, the second largest chemical site in the world.
AG&P Industrial, selected from among top 15 yards globally, to ship a total of 77 pre-assembled pipe rack modules and 58 pre-assembled support structures, weighing 10,443 MT for modules and 274 MT for support structures for INEOS Project ONE. AG&P Industrial’s last shipment is expected sail by February 2025.
5 Nov 2024, Project Cargo Journal
International transport and logistics company AsstrA recently completed the first phase of the OSBL module transportation for the Ineos Project One.
The company’s Industrial Project Logistics team moved a total of eight modules from the Philippines to Belgium via the Cape of Good Hope. Some of the modules measured 39 x 12 x 11 metres.
According to AsstrA, the delivery marks a milestone for Asstra Industrial Project Logistics as it is projected to transport almost 100 modules under this contract. It equates to more than 230,000 cubic metres of cargo.
The first batch of modules was transported by one of United Heavy Lift’s F900 heavy-lift multipurpose vessel, the UHL Flair.
Project One represents the largest investment in European chemistry in the past 25 years. The cracker, which will be the most sustainable of its kind, will be commissioned in 2026, according to Ineos. The facility will have a nameplate capacity of 1450kt of ethylene per year.
#ineos #projectone #cracker #antwerp #belgium #steamcracker