Guangxi Petrochemical Refining Project Exceeds Halfway

Site
Guangxi Petrochemical
Message Category
UserPic
Kokel, Nicolas
12/9/2024 9:02 PM



Photos:
▪️ Guangxi Petrochemical's 1.2 million tons/year ethylene cracking unit cracking furnace hoisting operation.

▪️ Builders carry out pipeline welding operations at the 50,000 tons/year hexene-1 unit.
▪️ Builders carried out modular pipeline gallery hoisting operations at the 270,000/600,000 ton/year propylene oxide co-production styrene unit.

Guangxi Petrochemical Refining and Chemical Integration Transformation and Upgrading Project Construction Progress Exceeds Halfway

China Petroleum News | 2024-11-27 16:04 | Beijing

On November 22, the 80-meter-high, 3,200-ton 1.2 million tons/year ethylene cracking unit cracking gas furnace module was in place.

On November 21, the last spherical tank in the chemical pressure tank area was successfully capped. On November 20, all towers of the 50,000 tons/year hexene-1 unit were hoisted.

On November 14, the installation of four modules of the cracked gasoline hydrogenation unit was completed...

Entering November, the Guangxi Petrochemical Refining and Chemical Integration Transformation and Upgrading Project has been successful, and many installation tasks have been completed according to the nodes. At present, the overall progress of the project has been completed by 62.81%, and the construction progress has exceeded half.

In order to improve the project construction progress and ensure the quality and inherent safety of the project, the Guangxi Petrochemical Refining and Chemical Integration Transformation and Upgrading Project strictly implemented the group company's "six-in-one" construction concept at the beginning of the design, and made the construction safer, more efficient and reliable through factory prefabrication and modular construction. In order to further promote factory prefabrication and modular construction, Guangxi Petrochemical has built "second construction sites" of varying sizes near the project construction site in accordance with local conditions - prefabrication yards, of which there are 8 pipeline prefabrication yards alone. The factory prefabrication rate of the steel structure of this project exceeds 95%, and with the concept of deepening factory prefabrication and modular construction, the operating efficiency has been greatly improved, the workload and safety risks on the construction site have been greatly reduced, and civilized construction on site has been further promoted.

#cnpc  #petrochina  #guangxi  #petrochemical  #ethylene  #steamcracker  #hexene  #gasoline  #hydrogenation  #china