The new podcast from ppPLUS. Join industry experts finding strategies for today's challenges.
Various Projects in the country, particularly in the Hydrocarbon Sector are subjected to a two stage approval process which is time consuming and has a history of impacting project viability. This also has an impact on the early project availability which can impact the speed of growth of the country.
In the first stage, typically known as Stage-I approval stage, the intent of the Project - Pre Investment Feasibility Report and its broad viability analysis is presented to the Board /GOI for clearance and review of recommendations of Pre Investment Feasibility Report. Given the prima facie merits of the Project viability, a Stage II approval is accorded for carrying out following activities as a minimum:
The DFR Schedules typically range between 6 to 9 months, depending upon the project configuration and the upfront involvement and cooperation of licensors to provide information on selected/recommended technologies. Invariably, DFR Preparation is carried out by conducting preliminary designs and broad estimation of equipment etc involved in the various facilities of the Complex, rather than taking recourse to actual process design of facilities envisaged in the Complex.
After submission of DFR, Projects have known to tread a rather uncertain course where time if often a causality. On the brighter side, there are instances where Projects have been approved for investment in a short period of 4-6 months, but generally final investment approval Stage-II Approval has often been found to be delayed. For Mega complexes entailing investments of over Rs. 60,000 to Rs 100,000 crores, such delays can be deleterious not only to overall health of the project, but sometimes may impact the very relevance and viability of the Project. Given the adverse impact these delays can have on Project viability, obsolescence of technology and inflationary pressures are other factors to be contended with. It is imperative therefore, that the time span between DFR submission and investment approval should be minimised. It may not be out of place to mention, that in these stages of the project it is the service component only which is under question, as no hardware commitment is to be made. Consequently it would be useful to utilise the intervening period between Stage-I clearance to Stage-II clearance and further between submission of DFR to investment approval that some front end work is initiated, without any hardware commitment, to save on precious project implementation schedule.
Activities to be overlapped between Stage I & Stage II approval of Projects
Given the fact that GOI has already identified Maharatnas / Navratnas in the Hydrocarbon Segment, a Pre Investment Decision prior to the Stage-II clearance i.e. expenditure in excess of the limits imposed along-with Stage-I clearance of the Project could be taken up by the respective Boards of Owners as an initiative to save on Project Schedule considering that the investment against the activities to be undertaken would be predominantly design driven without any tangible financial commitment against physical assets. Possibly a soft investment to the tune of 1% of the total Capital Cost envisaged for a Mega Grassroots Project only would be warranted to enable a schedule saving of 12-14 months on the overall project time cycle by carrying out Front End Engineering Detailing which is vital for initiating vertical Project Implementation.
Various measures such as deferred payments, post facto adjustments could also be explored between the Owner and the Consultant pending formal Board Approval. The essential part is to ensure, that this activity is initiated immediately after Stage I approval of the project. The major activities that need to be initiated are enlisted below. The activities listed pertain only to those items, which have a direct bearing on schedule and could prove crucial for initiating a head-start to the Project.
The above as may be inferred are all soft activities involving essentially Engineering and Licensing efforts. This is insignificant n the overall gamut of project framework but can have considerable impact by providing an upfront head start to a project, particularly Mega Projects where as much as 12-14 months could be saved in the overall implementation cycle of the Project. Surely a great plus!
Most of what is stated above is purely from personal experience in the Hydrocarbon Industry operating in PSU domains. Things in the Private sector could be a little different where Managing Licensor Concepts could be a factor to be additionally considered for the benefit of the Project schedules.
For the New Projects in Coal to Chemicals, Integrated complexes, Fertiliser complexes, Large scale Green Hydrogen/Green ammonia projects all these principles with little modification could be made use of. For a Nation which is at the cusp of a radical transformation saving time on the front end activities is a pre requisite!
#greenhydrogen #greenammonia #projectmanagement #projectplanning #investmentfeasibility #feasibilityreport #licensorselection #megacomplex #refinery #projectdesign #basicdesign #engineeringpackage #processflowdiagram #equipmentlayout #osbl #isbl #projectstages