logo
Butadiene Extraction Plant
Sinochem Quanzhou Petrochemical
logo
Sinochem Quan Zhou Petrochemical Co., Ltd.

7th Dec 2020: Commissioning of the new ethylene complex—which actually began in September 2020 with startup of the plant’s 400,000-tpy high-density polyethylene (HDPE) unit, followed by a 130,000-tpy butadiene extraction unit, as well as six other units—is part of the first phase of Sinochem Quanzhou Petrochemical’s broader second-phase expansion program at Quanzhou further increase crude processing capacity, chemical integration, and sophistication of operations at the complex, according to the operator’s website. (Source)

Asset Info

Category
Processing
Status
A
V
Additional Info

Utilization Planning
Asset Level
UoM
Metric Ton
Startup Date
09/2020
System Settings

User
UserPic  Kokel, Nicolas
Modified
11/2/2024 6:13 PM
Added
11/2/2024 6:12 PM
  Units Quick Access
Unit D Technology-Unit Category
Default Unit